Table 3.
Time spent developing and running the CME event
Item | Hours required for activity |
Developer activities | |
Planning | 15 |
Instructional design | 12 |
Coaching doctor participants | 20 |
Venue build (work with builder, troubleshooting, creating signage) | 10 |
Avatar design | 10 |
Communications (email, telephone, meetings) | 16 |
Technical issues/security | 8 |
Rehearsals | 6 |
Event | 3 |
Project director effort | 8 |
Speaker activities | |
Rehearsals | 6 |
Event | 3 |
Total person-hours | 109 |